Sparrows Point Environmental Reports
The Sparrows Point environmental reports section identifies environmental investigations submitted for the Voluntary Cleanup Program (VCP) including characterization and remediation plans that have occurred or are planned at the Sparrows Point property as part of the Administrative Consent Order (ACO).
The Maryland Department of the Environment and U.S
Environmental Protection Agency Region III (Agencies) have received and are
currently conducting a review of the Rod and Wire Mill Interim Measures
Supplemental Investigation Report (July 26, 2019) and the Former Coke Oven Area
Interim Measures Supplemental Investigation Report (August 2, 2019). The full reports are available in the links
below. The reports include the results
of the on-site groundwater samples and pore water and surface water samples
that were collected offshore in the vicinity of the Rod and Wire Mill and Coke
Oven Area. The on-shore and offshore water
sampling was requested by the Agencies to provide additional information to
evaluate the effectiveness of the current interim groundwater remedial measures
at the Rod and Wire Mill and Coke Oven Area. The results of these
investigations will be used by Tradepoint Atlantic (TPA) to prepare plans to
enhance the current interim measures.
Current human health direct contact exposures (swimming and
recreational activities) to contaminants detected in the surface waters
adjacent to the Coke Oven study area do not exceed MDE’s health-based standards
for recreational users.
Risks were
evaluated in the area with the highest detected concentrations of benzene and
naphthalene in the cove adjacent to Cell 3.
These findings from the additional
characterization conducted by TPA
build
upon the investigation of coke product residual impacts conducted in the Coke
Point Peninsula by the Port Administration (MPA) in 2011 (June 1, 2011 Public
Meeting Presentation provided below).
Although risks to recreational users do not exceed MDE health-based
standards,
MDE advises recreational users that potential
exposure to benzene and naphthalene exists in surface waters of the Cove Point
Cove area, as shown on Figure 22 of the Coke Oven Area report (link to figure
provided below).
Recreational users
fishing and crabbing in waters of the state should consult the MDE fish
consumption advisory recommendations at the following link:
The Agencies will be evaluating the additional corrective
measure plans currently being prepared by TPA.
The Agencies held a public information meeting on October 3,
2019 at 7:00 pm at the North Point Library to update the community on this
project.
Links to reports discussed during the meeting are posted below:
Storm Water Pollution Prevention Plan - Dated January 24, 2019
Quality Assurance Project Plan (QAPP) - Sparrows Point Terminal Site Report Revision 3, dated April 5, 2016
Sparrows Point Parcel Status Map, dated March 23, 2021
Response Action Plans (RAP)
Parcel A1- Approved RAP
Phase II ESA Work Plans and Reports
- Area A
- Parcel A1
- Parcel A2
- Parcel A3
- Response Action Completion Report (Metals Excavation), dated December 3, 2021
- Screening Level Risk Assessment rev. 0, dated August 30, 2019
- Lead and NAPL/Oil and Grease Delineation and Excavation Work Plan, dated February 2, 2017
- Lead and TPH/Oil and Grease Delineation and Excavation Work Plan, dated December 7, 2016
- Phase II ESA Report, dated July 8, 2016
- Former Rod and Wire Mill Phase II and PDI Work Plan, dated September 17, 2015
- Sub-Parcel A3-1
- Parcel A4
- Response and Development Completion Report, Rev. 1, dated September 13, 2021
- Response Action Completion Report-Cadmium Response Area, dated July 14, 2020
- Phase II - Minor Update Transmittal Letter, dated April 7, 2020
- Phase II Investigation Report rev. 3, dated December 20, 2019
- Proposed Excavation of Cadmium Impacted Soil, dated April 21, 2017
- Cold Mill Building Redevelopment Work Plan, dated November 29, 2016
- Phase II Work Plan, dated October 29, 2015
- Parcel A4-1
- Parcel A4-2
- Parcel A5, Parcel A9 and Grey's Rail Yard
- Greys Rail Yard Comment Response Letter, dated June 2, 2020
- Parcel A9 Comment Response Letter for Delineation/Characterization of Lead, dated December 11, 2019
- Parcel A9 Delineation/Characterization of Lead Work Plan, dated February 6, 2019
- Phase II Investigation Report, dated October 9, 2019
- Phase II Investigation Work Plan, dated August 23, 2017
- Parcel A6
- Phase II Investigation Report, dated June 23, 2020
- Phase II Investigation Work Plan, dated October 11, 2018
- Parcel A7
- Lead and Thallium Investigation Report, dated April 30, 2021
- Phase II Investigation Report Comment Response Letter, dated September 14, 2020
- Lead and Thallium Delineation Work Plan, dated September 1, 2020
- Phase II Investigation Report Comment Response Letter, dated July 8, 2019
- Phase II Investigation Report rev. 1, dated July 8, 2019
- Phase II Investigation Work Plan rev. 1, dated July 12, 2017
- Parcel A8
- Sub-Parcel A8-1
- Response and Development Completion Report, rev. 0, dated October 6, 2020
- Response and Development Work Plan Addendum Comment Response Letter, dated November 14, 2018
- Response and Development Work Plan Addendum, dated October 11, 2018 and Comment Response Letter
- Response and Development Work Plan, dated February 15, 2018
- Sub-Parcel A8-2
- Sub-Parcel A8-3
- Parcel A10
- CVOC Supplemental Investigation Report, Rev. 1 + Comment Response Letter, dated October 28, 2021
- CVOC Report, dated January 6, 2020
- Test Pitting Completion Report, dated July 14, 2020
- NAPL Delineation Completion Report, dated January 6, 2020
- Phase II Investigation Report Comment Response Letter, dated July 8, 2019
- Phase II Investigation Report rev. 1, dated July 8, 2019
- Phase II Work Plan, rev. 3, dated April 21, 2016
- Sub-Parcel A10-1
- Comment Response Letter: RADWP Addendum, dated March 29, 2021
- RADWP Addendum: Sub-Slab Soil Gas and Indoor Air Monitoring Program, dated February 2, 2021
- Supplemental Comment Response Letter: RADWP, dated January 20, 2021
- Response and Development Work Plan rev. 2, and Comment Response Letter, dated December 31, 2020
- Soil Gas Investigation Report, dated March 7, 2020
- Parcel A11
- Phase II Investigation Report rev. 1 and Comment Response Letter, dated May 22, 2020
- Monitoring Network Letter Report, dated March 5, 2020
- Phase II Investigation Work Plan, revised date May 18, 2016
- Sub-Parcel A11-1
- Sub-Parcel A11-2
- Soil Excavation Report - Southern Area, dated September 29, 2022
- Soil Excavation Report - Northern Area, dated August 26, 2022
- Soil Excavation Work Plan, Rev. 2, dated July 6, 2022
- Response and Development Work Plan, Rev. 3, dated June 30, 2022
- Parcel A14
- Phase II Investigation Work Plan, dated June 28, 2019
- Parcel A15
- Phase II Investigation Report, dated August 28, 2023
- Phase II Investigation Work Plan, Rev.1, dated September 30, 2022
- Parcel A16
- Phase II Investigation Report, dated August 11, 2023
- Phase II Investigation Work Plan, Rev. 1, dated September 30, 2022
- Parcel A17
- Phase II Investigation Report, dated October 8, 2020
- Phase II Investigation Work Plan, dated June 28, 2019
- Parcel A18
- Area B
- Parcel B1
- Sub-Parcel B1-1
- Sub-Parcel B1-2
- Parcel B-2
- Sub-Parcel B2-1
- Response and Development Work Plan revision. 1 and Update Letter, dated May 11, 2018
- Sub-Parcel B2-2
- Response and Development Work Plan rev. 3, dated March 18, 2020
- Sub-Parcel B2-3
- Comment Response Letter, dated August 6, 2020
- Response and Development Work Plan, dated June 19, 2020
- Parcel B-3
- Parcel B3-1
- Response and Development Work Plan, dated September 6, 2023
- Grading Plan, Rev. 0, dated December, 22, 2022
- Parcel B-4
- Sub-Parcel B4-1
- Development Completion Report, rev. 1 and Comment Response Letter, dated Jul. 15, 2020
- Development Work Plan, rev. 2, dated August 10, 2016
- Phase II Investigation Work Plan Parcel B4, Sub-parcel B4-1 and Sub Parcel B4-2 rev. 1, dated July 8, 2016
- Phase II Work Plan (Expedited Parcel), dated January 27, 2016
- Sub-Parcel B4-2
- Parcel B5
- Sub-Parcel B5-1
- Response and Development Work Plan Addendum + SLRA Update, dated July 6, 2021
- Response and Development Work Plan Addendum, dated December 14, 2018
- Response and Development Work Plan Addendum 1 Response to MDE/USEPA comments, dated February 19, 2018.
- Sub-Parcel B5-1 Response and Development Work Plan Addendum, rev. 1, dated February 19, 2018
- Sub Parcel B5-1 Response and Development Work Plan rev. 3, dated September 27, 2017
- Sub-Parcel B5-3
- Response and Development Work Plan, Rev. 1, dated September 11, 2023
- Parcel B6
- Sub-Parcel B6-1
- Response and Development Completion Report, rev. 0, dated December 11, 2020
- Response and Development Work Plan, rev. 2, July 7, 2017
- Sub-Parcel B6-2
- RADWP Addendum - Project Bayou, Rev. 1, dated May 17, 2022
- RADWP Addendum - Retail Area #3, Rev. 1, dated June 24, 2022
- RADWP Addendum - Flex Building, dated July 8, 2021
- RADWP Addendum (revised SLRA), dated June 28, 2021
- RADWP Addendum Modification Letter, dated October 24, 2019
- Marketing Center RADWP Addendum Comment Response Letter, dated October 24, 2019
- Marketing Center Comment Response Letter, dated August 12, 2019
- Interim Use Work Plan-Marketing Center, dated July 1, 2019
- Response and Development Work Plan Addendum, Retail Area #1, revision 2 and Update Letter, dated May 22, 2018.
- Response and Development Work Plan Response Letter, dated January 24, 2018
- Sub-Parcel B6-2 Response and Development Work Plan rev. 1, dated January 24, 2018
- Sub-Parcel B6-3
- RADWP Addendum, dated August 26, 2020
- Response and Development Work Plan, rev 1 and Comment Response Letter, dated June 17, 2020
- Sub-Parcel B6-4
- Response and Development Work Plan, dated October 1, 2020
- Parcel B6-5
- Parcel B6-6
- Parcel B7
- Parcel B7 Phase II Investigation Report, rev. 0, dated January 28, 2021
- Pre-Design Investigation Update Letter, dated October 14, 2020
- Pre-Development Investigation Work Plan- Baltimore County Fire Dept. Extension, dated May 29, 2019
- Pre-Development Investigation Work Plan, dated April 15, 2019 (Specific to potential Baltimore County property transfer area)
- Phase II Investigation Work Plan, dated August 23, 2017
- Parcel B7-1
- Response and Development Work Plan, Rev. 2, dated July 14, 2022
- Parcel B7/B25
- Phase II Investigation Report, dated March 25, 2021
- Phase II Investigation Work Plan, dated May 22, 2018
- Parcel B7-2
- Parcel B8
- Parcel B8-1
- Parcel B9
- Parcel B9-1
- Response and Development Work Plan, Rev. 5, dated April 26, 2023
- Parcel B11
- Parcel B13
- Interim Measures Work Plan, Rev. 1, dated July 7, 2023
- Work Plan Update Letter: Pre-development Supplemental Investigation, dated November 5, 2020
- Slag Characterization Completion Report rev. 1, dated September 14, 2020 and Comment Response Letter
- Stockpile Reuse Work Plan rev. 0, dated October 9, 2019
- Response Action Completion Report-Arsenic Removal, dated August 22, 2019
- Phase II ESA Report, dated April 19, 2017
- Phase II ESA Work Plan, Rev. 0, dated March 25, 2016
- Parcel B14
- 1st Quarter 2024 GW and SW Sampling Report, dated April 25, 2024
- Semi-Annual 2nd Half 2023 IM Report, dated January 24, 2024
- Interim Measure Work Plan, Rev. 2, dated March 29, 2022
- Baseline Surface Water Interim Measure Report, dated February 2, 2022
- Baseline Groundwater Interim Measure Report, dated January 28, 2022
- Phase II ESA Investigation Report, Comment Response Letter, dated June 30, 2021
- Phase II ESA Investigation Report, dated March 23, 2018
- Phase II ESA Investigation Work Plan, dated August 3, 2017
- Parcel B14-1
- Response and Development Work Plan, rev. 0, dated June 8, 2021
- Parcel B15
- Completion Report Comment Response Letter, dated Jul. 15, 2020
- Response and Development Completion Report, dated Apr. 3, 2018
- Expansion Notification, dated Apr. 4, 2017
- Response and Development Work Plan, dated Oct. 7, 2016
- Phase II Investigation Report, revision 1, dated Apr. 2, 2018
- Phase II ESA Investigation Work Plan, dated, Sept. 6, 2016
- Parcel B17
- Parcel B18
- Lead Excavation Letter, dated April 18, 2024
- Lead Excavation Completion Report, dated December 8, 2022
- Lead Excavation Work Plan, dated January 20, 2022
- Lead Supplemental Investigation Report, dated April 30, 2021
- Phase II Investigation Report, dated Aug. 3,2020
- No.10 Tank Area Investigation Report, dated Jan. 14, 2020
- No. 10 Tank Investigation Report Addendum, dated February 16, 2018
- Phase II Investigation Work Plan, dated September 22, 2016
- Parcel B19
- Supplemental AST Characterization Report, dated Aug. 12, 2020
- AST Characterization Work Plan, dated May 8, 2020
- Phase II Investigation Report, dated April 9, 2018
- Response and Development Work Plan, Rev. 3, dated September 27, 2017
- Phase II ESA Work Plan, dated August 9, 2016
- Sub-Parcel B19-1
- Parcel B20
- EMR Investigation Work Plan - Update Letter, dated January 20, 2023
- Phase II Investigation Report, rev. 0, dated January 14, 2021
- Phase II Investigation Work Plan, dated June 28, 2019
- Parcel B20-1
- Response and Development Work Plan, Rev. 4, dated June 29, 2023
- Parcel B21
- Parcel B21-1
- Response and Development Work Plan, Rev. 0, dated October 4, 2021
- Parcel B21-2
- Response and Development Work Plan, Rev. 0, dated October 1, 2021
- Parcel B22
- CMS Report and Comment Response Letter, dated February 18, 2021
- PORI Lagoon Excavation Completion Report, rev. 0, dated January 6, 2021
- PORI Lagoon Work Plan Letter, dated Sept. 1, 2020
- PORI Lagoon Characterization Report, dated Sept. 1, 2020
- Response and Development Completion Report, dated Jul. 15, 2020
- Logistics Center Grading Plan, dated Mar. 31, 2020
- PORI Lagoon Delineation Completion Report, dated December 4, 2019
- PORI Lagoon Interim Submittal, dated August 8, 2019
- PORI Lagoon Characterization Work Plan, dated February 26, 2018
- Road and Utility Investigation Report, dated January 10, 2017
- Delineation and Excavation of PCB and DRO Impacted Soil Report, dated December 22, 2016
- Road and Utility Investigation Report, dated December 16, 2016
- Road and Utility Investigation Plan, dated November 29, 2016 and Comment Response
- Phase II Investigation Report revision 1, dated August 8, 2019
- Phase II ESA Work Plan, revised date June 2, 2016
- Revised Response and Development Work Plan, dated January 16, 2017
- Response and Development Response to Comments, dated October 7, 2016
- Response to MDE/EPA Comments-Response and Development Work Plan
- Sub-Parcel B22-2
- Response and Development Work Plan, rev. 1, and Comment Response Letter, dated March 30, 2021
- Parcel B23
- PAH/PCB Delineation and Characterization Work Plan, dated November 3, 2020
- Phase II Comment Response Letter, dated July 17, 2020
- Phase II Investigation Report, dated December 20, 2019
- Lead Delineation/Characterization Work Plan, dated May 30, 2019
- Lead Based Paint Survey Report, dated May 29, 2019
- Phase II Investigation Report Work Plan, dated July 24, 2018
- Parcel B24
- Parcel B24-1
- Response and Development Work Plan, Rev. 2, July 21, 2022
- Coke Oven Area (B10, B11, B12, and B18)
- Container Terminal Phase II Report, Rev. 1, dated January 18, 2024
- West Area Phase II Investigation Work Plan, dated March 27, 2024
- Tin Mill Canal
- Maintenance Cleanup Plan revision 3, dated December 19, 2017
- Corrective Measures Study, dated June 16, 2017
- Sediment Characterization Report, Revision 3, dated January 4, 2018
- Tin Mill Canal Supplemental Work Plan, dated June 10, 2016
- Sediment Sampling and Analysis Plan Addendum, dated July 19, 2016
- Finishing Mills Groundwater Investigation
Phase I Environmental Site Assessment (ESA)-May 19, 2014
Site Conceptual Cleanup Plan
Contact Information
If you have questions or require assistance related to the above material, please contact Ms. Barbara Brown at 410-537-3493 or email to Barbara.Brown1@maryland.gov.