Back River Wastewater Treatment Plant is permitted to discharge treated wastewater under state-issued permit you can review
here. The state conducts inspections and data audits to ensure compliance with the permit requirements.
In the past, checking on how wastewater treatment plants were doing was a bit like getting a report card once a year—by the time you saw a problem, it had already been happening for a long time.
Now, we use an early warning system to monitor our most advanced plants every single month.
By tracking nutrients like nitrogen and phosphorus year-round, we can spot "red flags" before they become actual violations. Since weather or temperature can cause temporary dips in performance, we focus on three-month averages to identify real trends. If a plant is heading off-course, we send a warning letter immediately so the facility can fix the issue before the year ends.
This proactive approach has already been a success. For example, when major plants like Back River and Patapsco faced challenges, this system allowed us to step in with frequent inspections and guidance. This ensured they stayed within their legal limits and kept our waterways healthy. Read more about improvements
here.
Back River has achieved a complete reversal from its 2022 performance, reaching over 90% permit compliance in 2025 while consistently meeting effluent limits and reducing nitrogen pollution by more than 60% and phosphorus by 80%.
Compliance Activities
Inspection reports for Back River (Search site number 8449)
Discharge Monitoring Reports
Discharge Monitoring Reports User Guide
Discharge Monitoring Reports Data Dictionary
Daily E. Coli Data
(Updated monthly)
University of Maryland for Environmental Science Report
Consent Decree
The following improvements are in progress or completed under a
Consent Decree between the city and state:
Consent Decree Milestone |
Due Date |
Completion Date |
Replacement of air monitoring probes |
12/15/23 |
11/24/23 |
Install light and sign at Outfall 1 |
12/15/23 |
12/13/23 |
Repair and install dissolved aeration flotation system, thickened sludge pumps |
12/31/23 |
12/15/23 |
Clean and repair 8 primary settling tanks |
1/1/24 |
3/1/24 |
Repair gravity belt thickeners |
6/30/24 |
6/28/24 |
Repair and install centrifuge #4 |
12/31/23 |
10/1/24 |
Clean and repair all 11 primary settling tanks |
12/31/25 |
10/24/24 |
Complete sand filter rehabilitation |
12/31/28 |
Ongoing |
Complete rehabilitation of egg-shaped digesters |
9/16/27 |
Ongoing |